Kitchen Lead Times in Lebanon — How Long It Really Takes
How long does it actually take to get a new kitchen in Lebanon? From first consultation to final installation, here's an honest timeline broken down by route — locally manufactured, imported European, and budget carpentry.
Quick Answer
A locally manufactured premium kitchen in Lebanon typically takes 10–14 weeks from first consultation to completed installation. Imported European systems take 16–22 weeks. Budget carpentry can be faster but with significant trade-offs in quality and predictability.
- Locally manufactured premium (KITWOOD): 10–14 weeks total — 2–4 weeks design, 6–8 weeks production, 1–2 weeks installation
- Imported European premium: 16–22 weeks total — 2–4 weeks design, 10–14 weeks production and shipping, 2–3 weeks installation
- Budget carpentry: 4–8 weeks total but variable quality, no production drawings, limited after-sales
- Buffer for unexpected delays: add 2 weeks to any estimate for site readiness and trade coordination
Start your kitchen process at least 12 weeks before you need the kitchen functional. For renovation projects coordinated with broader construction, start the design process before demolition begins.
Why Lead Time Matters More Than Most Buyers Realise
Kitchen lead time is one of the most underestimated factors in renovation planning. Buyers focus on cost, materials, and design — and then discover at the end of the planning phase that the kitchen they want will not be available for four months, while the rest of the renovation is already underway.
In Lebanon, where renovation projects are often coordinated with the academic year, work cycles, or family events, this matters. A kitchen that arrives two months after the rest of the home is finished is a serious quality-of-life problem. A kitchen that arrives on schedule allows the entire project to land cleanly.
The lead time depends on which route you choose, and the differences are significant.
Phase 1 — Design (2 to 4 Weeks)
The first phase of any kitchen project is design — and this is where buyers can shorten or extend the overall timeline more than at any other stage.
A productive design phase looks like this:
• Week 1: Initial consultation, site measurement, brief gathering. The design team understands the room, your lifestyle, your budget, and any specific requirements. • Week 2: First design proposal — typically a 2D layout with material recommendations and a budget estimate. Feedback session to refine direction. • Week 3: Refined design with 3D renders, full specification, and detailed pricing. Client review. • Week 4: Final design approval, contract signature, and production order.
This can compress to 2 weeks for straightforward projects with a decisive client, or extend to 6–8 weeks for complex villa kitchens with multiple stakeholders. The single biggest factor is decision speed on the client side. Production cannot start until the specification is locked.
KITWOOD's design process at our Sin El Fil and Zouk Mosbeh showrooms is structured to support both fast and considered decision paths, depending on the project.
Phase 2 — Production (6 to 14 Weeks Depending on Route)
Once the design is approved and the production order is placed, lead time depends almost entirely on whether the kitchen is manufactured locally or imported.
KITWOOD LOCALLY MANUFACTURED PRODUCTION TIMELINE: • Week 1: Material procurement, production drawings finalised, machinery scheduling • Weeks 2–4: CNC cutting of carcasses, fronts, and accessories. Edge banding and sub-assembly. • Weeks 5–6: Hardware installation, internal accessories, finish quality control. Door and drawer assembly. • Week 7–8: Final factory assembly check, packaging for transport to site.
Total: 6–8 weeks from production order to site delivery. Possible to compress to 5 weeks for urgent projects against a small premium for production prioritisation.
IMPORTED EUROPEAN PRODUCTION TIMELINE: • Weeks 1–2: Order placed with European factory, slot scheduled in their production calendar • Weeks 3–8: European production (this varies — Italian and German factories typically run 6–10 weeks of production per order) • Weeks 9–11: Ocean freight from European port to Beirut port • Weeks 12–14: Customs clearance, transport to local warehouse, pre-installation staging
Total: 10–14 weeks from order to site delivery, with limited flexibility — the European factory's calendar and the shipping schedule are not negotiable.
The gap between these two routes is the single largest reason locally manufactured premium delivers so much faster than imported equivalents.
Phase 3 — Installation (1 to 3 Weeks)
Installation lead time depends on kitchen size and site readiness more than on the supplier:
• Standard apartment kitchen (3–5 metres of cabinets, no island): 3–5 working days • Open-plan kitchen with island and full-height storage: 7–10 working days • Full villa kitchen with multiple zones, island, larder, butler's pantry: 10–15 working days
On top of cabinet installation, allow time for:
• Worktop templating and installation: 1–2 weeks (the worktop is typically templated only after cabinets are installed, then fabricated and installed 5–10 working days later) • Appliance integration and connection: 2–3 days, coordinated with electrical and plumbing trades • Final adjustments and snag-list resolution: 1–2 days
The installation phase is where SITE READINESS becomes critical. If the floor is not finished, the walls are not painted, the electrical points are not in place, or the plumbing rough-in is not complete, installation cannot proceed cleanly. Buffer 1–2 weeks for site readiness coordination, regardless of supplier.
Total Realistic Timelines
Adding the phases together for a complete project from first consultation to functional kitchen:
KITWOOD LOCALLY MANUFACTURED PREMIUM: • Design: 2–4 weeks • Production: 6–8 weeks • Installation including worktop: 2 weeks • Site coordination buffer: 1–2 weeks • TOTAL: 11–16 weeks (typical: 12–14)
IMPORTED EUROPEAN PREMIUM: • Design: 2–4 weeks • Production and shipping: 10–14 weeks • Installation including worktop: 2–3 weeks • Site coordination buffer: 1–2 weeks • TOTAL: 15–23 weeks (typical: 17–20)
BUDGET LOCAL CARPENTRY: • Design: 0–2 weeks (often skipped entirely) • Production: 3–6 weeks • Installation: 1 week • Site coordination buffer: 1 week • TOTAL: 5–10 weeks (typical: 6–8)
The budget carpentry route appears fast — but this comes with no production drawings, no engineered material specification, no after-sales service, and no consistency between what is shown and what is delivered. The faster timeline reflects the absence of process, not efficiency.
For reference, a full breakdown of kitchen renovation costs in Lebanon covers both budget and premium routes.
How to Plan Your Project Timeline Properly
Practical guidance for planning a kitchen project in Lebanon:
1. START EARLY: If you need the kitchen functional by a specific date, work backwards 14 weeks for locally manufactured premium, or 20 weeks for imported. Add buffer.
2. LOCK THE DESIGN BEFORE DEMOLITION: Begin the design phase before the existing kitchen is removed. This way, production runs in parallel with renovation work, rather than after.
3. CONFIRM SITE READINESS WEEK BY WEEK: As production progresses, confirm with your contractor that floors, walls, electrical, and plumbing will be ready by the installation date. The biggest source of delay is not production — it is site readiness.
4. COORDINATE WORKTOP TEMPLATING EARLY: Worktop fabrication adds 1–2 weeks after cabinet installation. Make sure this is in the schedule.
5. AVOID 'JUST IN TIME' ASSUMPTIONS: Renovation schedules slip. A kitchen that arrives 3 weeks early can be stored at the factory until site is ready. A kitchen that arrives 3 weeks late means living without a kitchen for 3 weeks. Build in buffer.
Frequently Asked Questions: Kitchen Lead Times in Lebanon
**How long does a kitchen take from design to delivery in Lebanon?** A locally manufactured premium kitchen typically takes 11–16 weeks total. Imported European systems take 15–23 weeks. Plan accordingly.
**Can I get a kitchen faster than the standard timeline?** For locally manufactured premium, urgent projects can sometimes compress to 8–10 weeks total against a production-prioritisation premium. Imported European systems have very limited compression — the European factory and ocean freight schedules are not flexible.
**Why are imported kitchens so much slower?** The European factory's production calendar runs 6–10 weeks per order, then ocean freight to Lebanon takes 2–4 weeks, then customs clearance takes another week. None of these stages can be meaningfully accelerated.
**When should I start the design process?** Ideally, before demolition of the existing kitchen begins. This way, production runs in parallel with renovation work and the new kitchen is ready when the rest of the room is.
**What is the biggest source of delay in kitchen projects?** Site readiness — flooring, walls, electrical, and plumbing not being complete by the installation date. Production rarely runs late; site coordination often does.
To discuss your specific project timeline, book a consultation with our design team or visit the kitchens hub to start exploring options.
Ready to start your project?
Book a Free Consultation with KITWOOD Lebanon
Visit our showrooms in Sin el Fil (Saloumeh Roundabout) or Zouk Mosbeh (Jounieh Highway), or request a showroom consultation anywhere in Lebanon.







